Welcome to the Clayton High School Replacement Project

We're thrilled to share the exciting progress of the Clayton High School replacement project. This page will provide you with real-time updates as we transform CHS!

 

CHS Floor Plan - Level 1

CHS Floor Plan - Level 2

CHS Floor Plan - Level 3

 

278,000 SF

3-Story Building

New Athletics

MILESTONES

Construction Started = Dec. 16, 2025

Concrete Foundations Complete

Classroom Tower Steel Structure Finishing

Interior and Exterior Wall Framing Throughout

All Steel Complete = October 2026

New Building Completion = Nov. 19, 2027

Building Dry-In = December 2026

SCHOOL EVENTS


Schools Starts

Aug. 24, 2026


Topping Out

Oct. 1, 2026





Drone Footage

Traffic Updates

Traffic changes will occur throughout the construction of this project. Check here for updates.

 
 

Traffic Update

 
 

CHS Phasing Plan

 

CHS Final Conditions Plan

 